A1307 Godmanchester to Fenstanton resurfacing

We are posting to inform you that Highways England will be carrying out essential road resurfacing works on the A1307 in both directions between the above locations.

They plan to complete this work for five weeks from Monday 16 November to Wednesday 16 December, on weeknights only, working between the hours of 8pm to 6am, subject to weather conditions.

Due to works taking place both eastbound and westbound, their works have been split into three phases which are detailed below.

Phase 1: A1307 eastbound Pathfinder Link Road to Godmanchester, starting Monday 16 November to Wednesday 25 November (10 nights)

• Eastbound traffic travelling from Pathfinder Link Road will be diverted via, B1514/ Walden Road, Ermine Street /B1044, A141 to Brampton Hut Interchange, before joining the A1 southbound to join the A14 eastbound. Leave the A14 eastbound at junction 23 to travel on the A1198 into Godmanchester.

Phase 2: A1307 eastbound Godmanchester to St Ives, starting Monday 23 November to Saturday 12 December (2 weeks)

• Eastbound traffic will be diverted off the A1307 onto the A1198, then A428 eastbound before rejoining the A14 at Girton.

Phase 3: A1307 westbound from St Ives to Godmanchester, starting Monday 14 December to Tuesday 16 December (2 nights)

• Westbound traffic will be diverted from the St Ives Roundabout via Cambridge Road towards Cambridge Services, to then join the A14 westbound. Follow the A14 westbound before merging onto the A1 towards the Brampton Hut Interchange, at the interchange take the A1 southbound exit before rejoining the A14 eastbound until junction 23 and follow the A1198 to re-join the A1307.